Skip to content. Accessibility info.

News Archives

Public Service Announcement

Natural Gas Pipeline Installation – Portland Street

Tuesday, October 1, 2013 (Halifax, NS) - A natural gas pipeline installation is tentatively scheduled to begin the week of October 2, 2013, on Portland Street from Gaston Road to Prince Arthur Avenue. Work on the project will last approximately 2 weeks. Restoration will follow the project as it progresses.

There will be no on street work during peak hours of 7 a.m. – 9 a.m. and 4 p.m. – 6 p.m.

Motorists can expect one lane of traffic maintained in each direction from 9 a.m. to 4 p.m. Monday to Friday. Motorists should also expect delays and are requested to find alternate routes where possible.

Heritage Gas and HRM apologize in advance for any inconvenience.

-30-



Contact:
Heritage Gas Customer Line
1-877-836-7427

HRM Right of Way Services
490-6240

 

Above content last modified Thursday, November 02, 2023 at 11:40am.