Skip to content. Accessibility info.

Previous Construction Schedules

Construction activities related to the Harbour Solutions Project Sewage Collection System  (SCS) and Wastewater Treatment Plant  (WTP) sites.

Construction Schedule for 2004

Start Location Work Approximate Duration
April 2004 HRM land, Cogswell St. Interchange Tunnel access shaft 1 month


Lower Water St @ Maritime Museum of the Atlantic Combined sewer overflow (CSO) chamber 3 months


Hollis St from Sackville St to Morris St main collection line 4 months


DND property from Cornwallis to North St main collection line 3 months


Sackville St from Lower Water to Hollis St Tunnel access shaft & CSO chamber 6 months
May 2004 DND property from North St to Young St main collection line 3 months


Tunnel through Halifax CBD from Cornwallis St to Sackville St Tunnel 12 months


Atlantic School of Theology pumping station 8 months
June 2004 Todd property corner of Inglis and Barrington St. pumping station 9 months


Inglis St from Barrington to Young Ave main collection line 3 months
July 2004 HRM property off Upper Water St @ Casino CSO chamber 3 months
August 2004 Young Ave from Inglis to Southwood Dr. main collection line 2 months


Barrington St from Morris to Inglis St main collection line 4 months
September 2004 Pine Hill Dr from Tower Rd to Francklyn St main collection line 3 months


Utility bridge Tower Rd @ Southwood Dr. main collection line 4 months


Point Pleasant Park Balmoral pump station pump station 4 months
October 2004 HRM property Historic Properties CSO chamber 3 months